Do you determine payment based on billing date or equipment usage date?

Full question:

We are asking a subcontractor to sign a lien waiver of Feb. invoices. They refused because one invoice was not included. We rented equip from them during Feb but was billed in March. Do you go by billing date or date of equip usage to determine month due?

  • Category: Contracts
  • Date:
  • State: Texas

Answer:

The payment terms depend on the rental agreement. If the agreement doesn't specify when payment is due, courts will consider industry standards and previous dealings between the parties to interpret their intent.

This content is for informational purposes only and is not legal advice. Legal statutes mentioned reflect the law at the time the content was written and may no longer be current. Always verify the latest version of the law before relying on it.

FAQs

To fill out a subcontractor agreement, start by clearly identifying the parties involved, including the contractor and subcontractor. Specify the scope of work, payment terms, and deadlines. Include details about materials, equipment, and any necessary permits. Ensure that both parties sign and date the agreement. It’s also wise to consult with a legal professional to ensure compliance with state laws and to address any specific requirements.